Manufacturing Capabilities
Five processes run under a single inspection system. Each page lists the specification, the equipment behind it, and — equally important — the cases where you should use a different process instead.
Our in-house capabilities are 3-, 4- and 5-axis CNC milling, CNC turning with live tooling, sheet metal fabrication including laser cutting and welding, surface finishing through anodising and powder coating, and dimensional inspection on a CMM rated to ±0.002 mm. Heat treatment, forging, casting and non-destructive testing are subcontracted to audited suppliers and remain under our inspection gate.
Semiconductor Packaging
Automated power device packaging in Shenzhen: die attach, wire bonding, moulding, trim and form, 100% electrical test. 50 million units per month capacity.
Specification and equipmentReliability Testing
In-house reliability testing to JESD22 methods: HTRB, H3TRB, HT/HU, temperature cycling, thermal shock, solderability, HTSL, RSH and HPC.
Specification and equipmentSiC Device Assembly
SiC MOSFET and SiC Schottky die assembly for 175 °C operation: high-temperature die attach, copper bonding, high-Tg moulding and two-point RDS(on) test.
Specification and equipmentCustom Device Development
Custom power device development: die selection with foundry partners, DFN/QFN/TOLL outline qualification, custom marking and packing for OEM programmes.
Specification and equipmentTraceability & Quality System
Lot traceability from foundry wafer to shipping carton through ERP, MES and WMS records, under an ISO 9001:2015 quality system with PCN change control.
Specification and equipmentTolerance and cost by process
The same feature can often be produced three ways at three different price points. This table shows what each process realistically holds.
| Process | Typical tolerance | Surface finish | Economical quantity | Lead time |
|---|---|---|---|---|
| 3-axis milling | ±0.02 mm | Ra 1.6 µm | 1 – 10,000 | 5–10 days |
| 5-axis milling | ±0.005 mm | Ra 0.4 µm | 10 – 50,000 | 7–15 days |
| CNC turning | ±0.005 mm | Ra 0.4 µm | 50 – 100,000 | 7–12 days |
| Sheet metal | ±0.1 mm | As-formed or coated | 50 – 20,000 | 10–18 days |
| Surface finishing | N/A — adds 5–80 µm | Per specification | Any | 2–6 days |
Surface finishing changes dimensions: coating thickness is added to the part, so bores, threads and press fits must be specified with finish allowance in the drawing. This is decided at DFM, not after machining.
Send the part number and the operating conditions
Tell us the voltage class, current, switching frequency and what the device is replacing. You will get a datasheet, a parameter comparison at matched conditions, and a quotation with MOQ and lead time.